Thornlie Line Extension

Post by Mr OC Benz »

This is the thread for discussion specific to the Thornlie rail extension. For general Metronet policy discussion, please use the existing thread.

A project overview document has been released on the PTA's Project webpage. Key elements are:
- 17.5km extension of Thornlie Line from Thornlie to Cockburn Central
- Two new stations at Nicholson Road and Ranford Road
- 3-kilometre duplication of track between Beckenham and Thornlie
- 14.5 kilometre extension to connect Thornlie and Cockburn Central stations
- Significant modifications to Thornlie Station to convert to through-station and accommodate six-car trains
- additional platform and significant track work at Cockburn Central to independently service the extension without impacting existing Mandurah Line services
- Will become an important transport interchange hub, reducing demand at Murdoch Station.
- Explore value capture opportunities in the area.

Expected journey times:
Nicholson Road to Perth: 25-27 mins | Nicholson Road to Cockburn Central: 9 mins
Ranford Road to Perth: 28-30 mins | Ranford Road to Cockburn Central: 6 mins

Predicted boardings at the two stations in 2021: 3,120
Predicted boardings at the two stations in 2031: 4,352

Potential for an additional two million service kilometres and up to 20 new buses in the area to support the extension. At this stage, almost all bus services which connect with Murdoch Station to be retained.

Project Definition Plan expected to be completed by early 2018. Four year period to opening. A new dedicated METRONET website will be available in late 2017.
Thornlie Line Extension.png
Thornlie Line Extension.png (109.36 KiB) Viewed 14934 times

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

https://www.tenders.wa.gov.au/watenders ... pen-tender


Brief Description of Works: The project includes the design and construction of Karel Avenue Upgrades from Farrington Road to Berrigan Drive, including widening of the bridge over Roe Highway, a 2-lane dog bone roundabout arrangement for on and off ramps and upgrades to the freight rail bridge to accommodate the future Metronet line.

Pre-qualification Required: Roadworks R3 or higher, Bridgeworks B3 or higher and a financial rating of at least F25.

“The Code for the Tendering and Performance of Building Work 2016 (Building Code) applies to the building work associated with this project. By submitting an expression of interest in, or tender for, this project, you will become subject to the Code for the Tendering and Performance of Building Work 2016. Refer to the Building Code at employment.gov.au/building-code for further information.”

“It is a requirement of this project that any persons contracted to undertake the building work be accredited under the Australian Government Building and Construction WHS Accreditation Scheme established by the Building and Construction (Improving Productivity) Act 2016, at the time of entering into the contract for the building work and while the building work is being carried out.

Tenderers intending to submit a bid as a Joint Venture must review the additional requirements as outlined by Section 26(1)(f) of the Fair Work (Building Industry – Accreditation Scheme) Regulations 2016 by the Federal Safety Commission (located at http://www.fsc.gov.au)”

FLOREAT 90
Posts: 13
Joined: Sat Feb 04, 2017 3:49 am

Re: Thornlie Line Extension

Post by FLOREAT 90 »

In regards to the Thornlie to Cockburn rail extension, I was considering if this could coincide with the current "W" pattern services on the Mandurah line, which terminate at Cockburn, becoming "K" pattern services and extending to Rockingham. There is currently only one train per weekday operating to this pattern. This could save a lot of layover congestion at Cockburn and provide more frequent weekday rail services to the growing areas between Cockburn and Rockingham.

User avatar
Mr OC Benz
Moderator
Posts: 5725
Joined: Sat Jun 06, 2009 2:18 am
Favourite Vehicle: Anything German
Location: Sydney, NSW
Contact:

Re: Thornlie Line Extension

Post by Mr OC Benz »

Layover congestion won’t be any worse than it is now at Cockburn given the Thornlie Line would be operated independently with its own track and platform and not rely on existing Mandurah Line tracks/platforms. Exception to this is special event trains from Mandurah which could run direct to Perth Stadium via Thornlie.

bullswool
Posts: 4
Joined: Sat Jan 27, 2018 3:31 am

Re: Thornlie Line Extension

Post by bullswool »

The key question for me is will the Thornlie Line service continue to run every 15 minutes in peak, or will it finally run every 10?

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »


User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

The METROCONNEX consortium (Acciona, Aurecon, Clougj, Georgiou & WSP) has strongly been rumoured to have won the contract to build the Yanchep & Thornlie extensions with a major announcement from Minister Saffioti expected tomorrow


https://metroconnex.com.au/

User avatar
Bus Suggestions
Posts: 441
Joined: Sun Jul 24, 2016 8:05 am
Favourite Vehicle: Something with a ZF Ecomat
Location: The West
Contact:

Re: Thornlie Line Extension

Post by Bus Suggestions »

NEWest (CPB Contractors & Downer EDi) have officially won the contracts for the Thornlie-Cockburn Link & the Yanchep Rail Extension, announced at an event today to mark the start of construction on the Yanchep Rail Extension.
METRONET Website wrote:NEWest Alliance to build two METRONET projects
23 November 2019

The preferred alliance to construct both the Yanchep Rail Extension and Thornlie-Cockburn Link is NEWest Alliance.

The announcement was made at an event to mark the start of early works for the Yanchep Rail Extension.
Made up of CPB Contractors and Downer EDI, NEWest Alliance will work closely with the Public Transport Authority to progress the designs and construction schedule once the contract is signed next month.

Together the projects are set to create 3000 jobs and once operational will give residents of the northern and eastern suburbs greater access to employment and training, entertainment and recreation hubs.

The Yanchep Rail Extension will add 14.5km to the existing Joondalup Line, with stations at Alkimos, Eglinton and Yanchep. With early works already underway, construction will commence next year, and the first trains are expected to be running in 2022.

The Thornlie-Cockburn Link will close a 14.5km gap in the eastern rail corridor by linking communities between the Mandurah and Armadale lines. Stations will be built at Ranford Road and Nicholson Road in Canning Vale, and significant upgrades made to both Thornlie and Cockburn Central stations. Early works on the project will begin later this year.

For more information visit the Yanchep Rail Extension or Thornlie-Cockburn Link project pages.
[Insert Signature]

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

ImageImage
Image

Few artists impressions of Alkimos & Yanchep stations. Yanchep station has a 3 platform terminus


Sent from my iPhone using Tapatalk

User avatar
Squiddy
Posts: 305
Joined: Thu May 04, 2017 5:20 pm
Favourite Vehicle: Anything with new bus smell!!
Location: Perth
Contact:

Re: Thornlie Line Extension

Post by Squiddy »

TP1462 wrote:Yanchep station has a 3 platform terminus


Sent from my iPhone using Tapatalk
Got a source for it having three platforms other than the artist's impression? Have seen conflicting information on this, such as this fact sheet (admittedly, issued well over a year ago) which says there will only be two:

https://www.metronet.wa.gov.au/Portals/ ... 3zGLMRgxeU
Currently working on my bus photography site where I'm aiming to photograph every Transperth bus in Perth - have (almost) everything!

Check out https://squiddysbuses.com/ !!! :D

User avatar
Mr OC Benz
Moderator
Posts: 5725
Joined: Sat Jun 06, 2009 2:18 am
Favourite Vehicle: Anything German
Location: Sydney, NSW
Contact:

Re: Thornlie Line Extension

Post by Mr OC Benz »

The Project Definition Plan states the ultimate design for Yanchep is for three platform faces to provide for operational efficiency and to handle expected patronage growth. There will definitely be two platform faces from day 1 but whether the third is also built at the same time remains to be seen. Not necessarily required from day 1.

There is also reference to a three platform face design for Alkimos but this is even less likely from day 1 but potentially necessary future proofing to accommodate a future East Wanneroo Line branching north of Clarkson.

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

Image


Sent from my iPad using Tapatalk

User avatar
Zidanehartono
Posts: 288
Joined: Thu Dec 17, 2015 10:48 am
Favourite Vehicle: Custom CB80
Location: STW9 HQ (Nine Perth Studio)
Contact:

Re: Thornlie Line Extension

Post by Zidanehartono »

It's been announced that the contract goes to NEWest Alliance with early works already commenced on the Thornlie-Cockburn Link.

Source:https://www.metronet.wa.gov.au/news-inf ... t-signed-1
The one who catches the Perth Stadium bus like an illegal immigrant by only to gunzel for buses & trains and/or to go anywhere else.

TP3085 always operates the first 654 trip to Perth Stadium.

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

Level crossing removal contracts awarded
Announcing the preferred proponents for two new contracts are important steps to removing up to seven level crossings on the Armadale line.

As early works start on the Denny Avenue Level Crossing Removal project, Downer EDI has been chosen as the preferred proponent to build the major rail components.

This is the first of two construction packages, with the road component contract set to be awarded in early 2020 for major works to begin next year. Downer EDI and Decmil are the two shortlisted proponents for this road package of works.

Planning to remove another six level crossings along the Armadale Line is also progressing with Jacobs named as the preferred proponent to develop the business case.

The expanded project scope for the business case includes the crossings at Oats Street, Mint Street and Welshpool Road in one package, and Wharf Street, Hamilton Street and William Street in another.


https://www.metronet.wa.gov.au/news-inf ... -awarded-1




Sent from my iPhone using Tapatalk

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

Appears though construction has started on the extension the inside lanes of the freeway have been closed from the Berrigan Drive bridge, looks like the 2 additional tracks will be laid the same time as the North Lake road bridge which is well advanced now too.


Sent from my iPhone using Tapatalk

Merc1107
Posts: 683
Joined: Sat Jul 07, 2012 8:38 am
Favourite Vehicle: High Floor Buses
Location: Perth

Re: Thornlie Line Extension

Post by Merc1107 »

Apparently some of the freeway widening works around Cockburn were performed with the impending construction of the TCL in mind, although I haven't seen any plans for the work (or what is fast becoming the finished product) so not sure what aspects of the roadworks were going to accommodate the future platforms/tracks at Cockburn.

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

Merc1107 wrote:Apparently some of the freeway widening works around Cockburn were performed with the impending construction of the TCL in mind, although I haven't seen any plans for the work (or what is fast becoming the finished product) so not sure what aspects of the roadworks were going to accommodate the future platforms/tracks at Cockburn.
The intention is to tie the bridge structures for the Armadale North Lake road bridge and all of the infrastructure relating to the TCL extension by keeping one lane closed from Berrigan Drive in either direction so they don’t have to go back later the lane closure also allows work for rail widening under the bridge to take place and realignment of the crash barriers. Thornlie extension trains are meant to run independently from the Mandurah line on 2 separate tracks from the tunnel then back into a single track upon arrival at the dock platform so there will be 2 cockburn shuttles if that makes sense only footy and event trains will access the spur


Sent from my iPhone using Tapatalk

User avatar
TP1462
Posts: 989
Joined: Sun Aug 07, 2011 5:43 am
Favourite Vehicle: B7RLE, OC500LE, 0305, B10M.

Re: Thornlie Line Extension

Post by TP1462 »

The platform extension and realignment of rail crossovers can be managed by full and partial shutdowns of the inner Mandurah line


Sent from my iPhone using Tapatalk